Violet Bank and Ravensbarrow Lodge

11th May 2010

VIOLET BANK, Hawkshead


























 




 




 




 


 
 
 
 
 
 
 
 
 
 
 
 
 

Since our last blog on Violet bank things are moving along nicely.

The new oak trusses have been constructed on the floor and erected with the oak purlins, which now form the roof. John Martin, our local joiner/craftsman, I think you will agree, has done a fine job.












 







































 









 









 






The roof spars are now also in place with a procters breathable felt covering. Much of the stonework immediately around the new timbers had to be rebuilt, as it was unsound and all carefully put back to match what was there. All the roof areas are now ready to take the carefully sorted and re-dress original slates, as much of the slate will be reused and a quantity of new slate to match the existing will be used to make up for short fall.


















 
 









 









 









 


























 
The stone facing work on the kitchen/bedroom is taking shape and this will also receive a new chimney stack as near to the original as possible, with a lead tray at roof level, slate tabling between the lead and stonework forming a drip and break.
































 




 

 
The out house has now also been stripped of its slate and roof timbers, a new concrete floor was laid, in readiness for the hot water tanks and a bio mass boiler, all have to go in before the roof is installed.
























 













 






 
In the mean time internal floors in the barn will be replaced with new timbers and steel floor beams, areas of walls will be rendered prior to tanking.
































 



 
 
A new purpose built timber building will also be erected in the next few weeks to give us a little onsite storage and long term timber storage for the bio mass heating system.

 

RAVENSBARROW LODGE, Cartmel Fell


















 
It is all but finished for us internally where all second fix work is now well underway.
 
Externally the underground oil tank has been installed behind the garage retaining wall, the boiler and plant room now has a soil roof covering which can now be grassed over to bring the woodland back to the building line.

































 



A higher level walkway has also been constructed next to the old barn to provide access to the lower lean-to building and a small stone arch has also been constructed over the stream to form a feature, the stream water will then flow into an old limestone trough salvaged from the original demoliton works.
































 







 




 




 




 





 




 




 




 





 




 




 




 


The front lawn is also being transformed with a new covering of top soil and stone retaining wall to the driveway and steps down onto the front lawn.




































The garage has also been plastered out on the first floor to give the owner a nice studio area for painting and office work. And with a good size garage at ground level lots of room for cars etc.

The next job is building of the stone steps to the rear garden area and lots of nice feature seats built into the stone walls and dotted around the garden with reclaimed oak incorporated onto the seats to soft the stonework.